Activity/Period |
Average time |
Responsible party |
Submission of questions / clarification
meeting |
80 days from the publication of the call (will be defined in the tender documentation) |
Ministry of Environment and Physical Planning |
Preparation / submission of bids |
90 days from the publication of the call (will be defined in the tender documentation) |
|
Evaluation of bids / bringing decision |
20-30 days from the public opening |
Ministry of Environment and Physical Planning |
Lodging of appeals |
8 days from the day of receiving the decision |
|
Appeal procedure (if applicable) |
20-30 days from the deadline for lodging appeals |
Public Procurement State Appeal Commission |
Founding local company / paying one-time concession fee |
30 days from day of receiving the final decision |
Central Register |
Obtaining license to use water |
45-60 days from day of receiving the final decision |
Ministry of Environment and Physical Planning |
Signing of concession contract |
?? from day of receiving the final decision |
Ministry of Environment and Physical Planning |