Planning Phase (approx: 2 years)
1. Approval to build a new renewable energy power plant with capacity above 10MV
60 days |
2. Resolving property right issues
Time undefined
|
3. Preparation of State Urban Plan Documentation, Architectural Design $ Conceptual Design
Time undefined
|
4. Enviromental Impact Survey
Time Undefined
|
Construction Phase (approx: 1 year)
5. Construction permit
40-60 days
|
6. Electricity generation licence
Est. 60 days
|
7. Permit for Use
40-70 Days
|
8. Connection to power distribution system
8 days (for decision) Time Undefined (for connection)
Connection to power transmission system
Time Undefined
|
Commissioning Phase (approx: 6 months)
9. Entry into the register of Renewable Energy Power Plants
40 Days
|
10. Provisional decision for acquiring power generator
40-50 days
|
11. Decision for acquiring status of preferential power generator and approval for use of feed-in tariff for electricity generation from RES
40-60 Days
|
12. Entry in to power purchase agreement with electricity market operator MEPSO for selling of electricity produced by RES preferential power generator
30 Days
|
|